Duodatong Charging Station Subproject

In December 2019, the GFP Project issued a loan of CNY 9 million to Beijing Duodatong Energy Technology Co., Ltd. to finance its construction of two charging stations in Beijing. 70 DC fast charging piles and 15 box-type transformers will be installed. Moreover, with easy access to the parking system, the subprojects aim to create intelligent and convenient parking and charging places, which will further enhance user experiences. After completion, the subprojects are expected to reduce CO2 by 28,000 tons and SO2 by 1.7 tons per year through gasoline substitution. As Beijing Duodatong Energy Technology Co., Ltd. is a small and medium-sized enterprise in Beijing, the subproject demonstrates I&G’s determination and efforts in supporting green SMEs.

Project Name Charging capacity(kW·h/day) Charging time(h/d) Numbers of charging cycle (/d) Gasoline savings(t/d) Date
盈坤世纪超级充电站 8593 218 463 5.17 Fri Jul 26 00:00:00 CST 2024
回龙观超级充电站 4038 93 185 2.43 Fri Jul 26 00:00:00 CST 2024
宝隆超级充电站 25858 412 648 15.55 Fri Jul 26 00:00:00 CST 2024
居然之家超级充电站 10028 244 370 6.03 Fri Jul 26 00:00:00 CST 2024
财满街超级充电站 5107 134 247 3.07 Fri Jul 26 00:00:00 CST 2024
盈坤世纪超级充电站 6362 178 419 3.82 Thu Jul 25 00:00:00 CST 2024